How often does a climbing wall need inspecting?

The short answer is: on three different timescales, and two of them belong to the people who run the wall. Most venues we speak to think they have one inspection. They have three.

BS EN 12572 describes three levels of inspection, and it describes them the same way for roped walls and for bouldering walls. They differ in how deep they go, how often they happen and who does them.

The first is the routine visual inspection. It is a look from the ground for the obvious: a loose hold, damaged matting, something missing, something left where a climber could land on it. On a busy wall, or one that gets misused, the standard says that can mean every day. It takes minutes and it is done by your own staff. Write it down, because the record is the only thing that shows it happened.

The second is the operational inspection. It is a closer look at how the wall and its parts are working and wearing. This is the one place the standard gives a figure: every one to three months, or whatever the manufacturer's instructions say. It has to be documented.

The third is the main inspection. It is hands-on, across the whole structure: foundations, frame, surfaces, and generally the inside of the wall. It is the one carried out by a competent person, and it is the visit most people mean when they ask for a climbing wall inspection.

Here is the part people get wrong. The standard in force does not put a number on the main inspection. It points to the manufacturer's instructions for your wall. Twelve months is the common convention in this country. It is not a clause of the standard, and it is worth knowing the difference if anyone ever asks you to justify your programme.

So your interval is whatever your manufacturer's instructions say. If you do not hold them, and for older walls many people do not, then the interval you are working to is an assumption, and it should be written down as one. An interval recorded as assumed is an honest record. A date with nothing behind it is not.

That may change. The standard is being revised, and one of the drafts would give roped walls a default. Nothing is published yet, and we have written about what the drafts propose separately.

What the standard does ask for today is a notice on the wall showing the date of the next main inspection. You can go and look at that now. We have written about that notice too.

Equipment keeps its own time. Auto-belays, harnesses and the rest are checked at the intervals their makers set, which are not the wall's intervals. See auto-belay inspection.

The three levels work as a system. Any one of them alone leaves a hole.

Our free seven-page guide sets out what BS EN 12572 actually asks of the person responsible for a climbing wall — and what it does not: get the guide.