BS EN 12572 is being revised: what the drafts change, and what they don't
The standard that climbing walls are built and inspected to is being rewritten. All three parts of BS EN 12572 went out as drafts for public comment in July 2025, and comments closed that August. Nothing has been published since. Until it is, the 2017 editions are the ones in force, and they are the ones we inspect to.
A draft is not a standard. Each one says so on its cover, and what comes out at the far end can differ from what went in. So what follows is what the drafts propose, not what the standard will say.
For anyone who looks after a wall, the change that matters most is where inspection sits. In the 2017 editions the inspection requirements are in an annex at the back: Annex G for roped walls, Annex F for bouldering. In the drafts they move into the main body as a clause of their own, Clause 8 in Part 1 and Clause 9 in Part 2. The Part 1 draft also keeps its Annex G, so for roped walls the same subject appears twice.
For bouldering, what the new clause asks for has barely moved. The same three levels are there, routine visual, operational and main, and the main inspection is still at whatever interval the manufacturer's instructions give. Moving from annex to clause changes how prominent inspection is, not what it is.
For roped walls the two places do not agree. The new clause leaves the interval for the main inspection to the manufacturer, as the 2017 edition does. The annex kept behind it introduces a default period. That is a draft contradicting itself, and it reads like an edit left unfinished, which is the best reason not to act on one. But it is worth watching. If a default survives into the published text, it will be the first time the standard itself has put a number on the main inspection.
Bouldering gets more attention than that. The Part 2 draft adds a clause on documentation for the impact area, so the matting has its own paperwork alongside the wall's, and it revises the table and figure that set how far the impact area has to reach. We are not going to quote draft figures, because they may not survive. But the floor is where the revision is looking, and on the bouldering walls we have inspected, the floor is where the findings have been.
For roped walls, the Part 1 draft adds to what is asked of the top protection point on each line and of the technical documentation handed over with a wall. Both drafts add an allowance for extra load on the climbing surface. Part 3, which covers holds, is being revised alongside them.
The reason to care before anything is published is numbering. Every report that cites a clause or an annex of the 2017 edition is citing a layout that is going to move. In today's Part 2, Annex F is inspection and maintenance. In the draft, Annex F is a test for the way mats are joined. So a reference to Annex F with no edition beside it would not just be out of date. It would point at a different subject altogether.
None of that makes an existing report wrong. A report names the edition it was assessed against and stays a true record against that edition. How an existing wall is treated once a new edition is out is a question to answer from the published text, when there is one.
As for when: there is no date from BSI. Its own project pages show the public comment stage finished and the stages after it, resolving the comments, approval and publication, still to come. One standards catalogue lists early 2027. Treat that as a forecast.
Nothing needs doing to your wall because of a draft. Two things are worth doing anyway, and neither needs us. Check that your last inspection report names the edition it was assessed against. And find the manufacturer's instructions for your wall, because the old edition and the new one both lean on them.